# Get a full payment schedule written into the contract

Write every payment date for the whole job into the contract: application, due date, notice deadlines and final date for payment. If the contract only gives you a formula, turn it into a dated schedule and get the payer to confirm it in writing.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 9 October 2026 · About 2 min readShare

## Why

A formula is only a schedule once someone applies it, and two people often get different dates from it. Your QS counts from the application date and theirs from the due date. One of you forgets a bank holiday. The argument surfaces on the day a notice is due, and one wrong date can be enough to lose a month's payment. A verified schedule reduces counting disputes, but still needs to follow a compliant payment mechanism.

## How do I do it?

1.  Write out the application date, due date, payment notice deadline, pay less notice deadline and final date for payment for the first month.
2.  Roll the same counting forward for every month to the expected end of the job, using the applicable day-count and holiday rules. Include a mechanism for work continuing beyond the listed cycles.
3.  Send the schedule to the payer and ask it to confirm the dates in writing, or say where it counts differently.
4.  Have the agreed schedule attached to the contract, or referred to in it, before you sign.
5.  Put every date on the schedule in the diary the day it is agreed.

Our [Construction contract management](<https://www.quantsurv.com/quantity-surveying#client-types>) turns the applicable payment clauses into a checked schedule with responsibility for each action.

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)

[Browse the Library](<https://www.quantsurv.com/library>)