# Know your right to suspend, and its procedure

For an in-scope contract, an unpaid section 111 payment obligation can support statutory suspension after at least seven days' compliant notice stating the grounds. Check the actual sum due, service and all conditions before stopping.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 9 October 2026 · About 2 min readShare

## Why

Suspension can be a significant remedy for an unpaid party, but using it incorrectly can create serious risk. Pull a crew off site on a Friday because the money has not come, and your unpaid sum becomes an allegation of walking off the job. The right under [section 112 of the Housing Grants, Construction and Regeneration Act 1996](<https://www.legislation.gov.uk/ukpga/1996/53/section/112>) depends on failure to satisfy the section 111 payment obligation by the final date. That can include failure to pay a sum reduced by a valid pay less notice. At least seven days' compliant notice specifying the grounds must precede suspension; take advice on any disputed condition before acting.

## How do I do it?

1.  Confirm that the Act applies, identify the operative sum after any valid pay less notice, and verify that the section 111 obligation remains unpaid after the final date.
2.  Read the contract's suspension clause, check it against the Act, and take advice if they differ.
3.  Serve written notice of your intention to suspend, stating the ground, on the named people by a method the contract allows, and keep the proof of sending.
4.  Verify service and the statutory day-count rules, give at least seven days' notice and do not stop before the applicable period has run.
5.  Record the costs of suspending and remobilising from the first day, because you will need them later.

Our [Overdue payment recovery](<https://www.quantsurv.com/claims/overdue-payment-recovery>) assembles the payment and notice record for considering suspension, with legal advice where the right is uncertain.

## Sources

1.  [Housing Grants, Construction and Regeneration Act 1996, s 112 (Right to suspend performance for non-payment)](<https://www.legislation.gov.uk/ukpga/1996/53/section/112>). legislation.gov.uk.

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)

[Browse the Library](<https://www.quantsurv.com/library>)