# We haven't checked late-payment interest or recovery costs

We have been paid late more than once, and nobody has worked out what interest or costs we could claim.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

Late payment may give you a right to interest, compensation or recovery costs under [the Late Payment of Commercial Debts (Interest) Act 1998](<https://www.legislation.gov.uk/ukpga/1998/20/contents>). But the remedy is not the same for every contract or invoice. Your contract may set its own interest, and how that sits with the Act needs checking before you assume anything.

The start date matters too. Work out when each payment actually became late, rather than counting from the invoice or the due date by habit.

If interest is available but left uncalculated, a potentially recoverable part of the account remains unresolved. A round sum added to the final account is easy to refuse. Even a sound calculation does not guarantee you will be paid it, or that the payer will change its habits.

## What do I need to do?

1.  Check the contractual interest clause and whether a statutory remedy is available.
2.  Record each debt, final payment date, actual receipt date and applicable rate.
3.  Calculate interest separately for each payment, retaining the calculation and source records.
4.  Check eligibility for any additional compensation or costs, avoid double recovery and include supported amounts in the written request.

To have this done for you, see our [Overdue payment recovery](<https://www.quantsurv.com/claims/overdue-payment-recovery>) and [Payment timetable and notice process setup](<https://www.quantsurv.com/claims#client-types>) services.

## Sources

1.  [Late Payment of Commercial Debts (Interest) Act 1998](<https://www.legislation.gov.uk/ukpga/1998/20/contents>). legislation.gov.uk.