# What happens after an adjudication decision?

Read the decision's payment and fee directions, reconcile receipts and obtain advice promptly if it is not complied with. Enforcement or a later dispute is a separate step.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## The answer

An adjudicator's decision is generally binding pending final resolution by agreement, court or arbitration. Record what was decided, the sum, interest, payment deadline and actual fee allocation. Fee responsibility and any liability to the adjudicator follow the applicable rules and appointment terms, not a universal winner–loser rule.

If payment does not arrive, speak to your solicitor about enforcement, timing, costs and any challenge. Courts commonly enforce adjudication decisions, but jurisdiction, procedural fairness and other case-specific issues can matter; recovery is not guaranteed.

A later true-value adjudication may be possible after compliance with a notified-sum award that left true value undecided. It is not a right to re-adjudicate the same dispute already decided. Preserve the first decision and referral scope so your representative can identify what remains open.

Update the account to show sums awarded, payments received, interest and remaining differences without double counting. Keep that reconciliation separate from any final settlement or later proceedings.

[Overdue payment recovery](<https://www.quantsurv.com/claims/overdue-payment-recovery>) can reconcile the decided sum and interest with receipts and support agreed follow-up. Court enforcement belongs with your solicitor.

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)

[Browse the Library](<https://www.quantsurv.com/library>)