# How does NEC4 Option Y(UK)2 work?

Y(UK)2 links the relevant NEC payment mechanism to the Construction Act. Use the provision in your actual form; ECS and ECC periods and ECSS arrangements must not be assumed identical.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## The answer

Y(UK)2 links the relevant NEC payment mechanism to the Housing Grants, Construction and Regeneration Act 1996. Use the provision in your actual form; ECS and ECC periods and ECSS arrangements must not be assumed identical.

Identify the payer and payee under your agreement and check who is authorised or required to assess, certify and issue each notice. A job title alone does not establish or disprove authority: read any delegation and the actual wording.

Map clauses 50 and 51, the relevant UK payment provisions, Contract Data and amendments onto the due date, notice deadline and final date. [Housing Grants, Construction and Regeneration Act 1996, section 110A](<https://www.legislation.gov.uk/ukpga/1996/53/section/110A>) requires the relevant payment notice's sum and basis. If a required payer notice is missing, verify whether a compliant application has the necessary default-notice effect or whether [section 110B](<https://www.legislation.gov.uk/ukpga/1996/53/section/110B>) requires a further notice.

To pay below the operative notified sum, a valid pay less notice must meet [section 111](<https://www.legislation.gov.uk/ukpga/1996/53/section/111n1>) and the applicable contractual requirements. Its deadline is separate from the final date; a notice delivered before payment is due may still be too late.

A proposed suspension requires a separate check under [section 112](<https://www.legislation.gov.uk/ukpga/1996/53/section/112>), including the unpaid payment obligation and at least seven days' compliant notice. Check how the actual contract deals with the resulting time and cost, including any compensation-event provision, without bypassing its procedure.

The useful output is one verified cycle showing the documents, authority, dates and amount payable. Keep a valuation challenge separate from the obligation to pay the notified sum.

Our [Construction contract management](<https://www.quantsurv.com/quantity-surveying#client-types>) records how the selected secondary option affects the due date, notices and final date for payment.

## Sources

1.  [Housing Grants, Construction and Regeneration Act 1996, s 110A (Payment notices: contractual requirements)](<https://www.legislation.gov.uk/ukpga/1996/53/section/110A>). legislation.gov.uk.
2.  [Housing Grants, Construction and Regeneration Act 1996, s 110B (Payment notices: payee’s notice in default of payer’s notice)](<https://www.legislation.gov.uk/ukpga/1996/53/section/110B>). legislation.gov.uk.
3.  [Housing Grants, Construction and Regeneration Act 1996, s 111 (Requirement to pay notified sum)](<https://www.legislation.gov.uk/ukpga/1996/53/section/111n1>). legislation.gov.uk.
4.  [Housing Grants, Construction and Regeneration Act 1996, s 112 (Right to suspend performance for non-payment)](<https://www.legislation.gov.uk/ukpga/1996/53/section/112>). legislation.gov.uk.

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)

[Browse the Library](<https://www.quantsurv.com/library>)