# Can I claim late payment compensation as well as interest?

Where statutory late-payment interest applies, fixed compensation is £40, £70 or £100 according to the qualifying debt's size. Additional reasonable recovery costs are limited to the amount exceeding that compensation.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 9 October 2026 · About 2 min readShare

## The answer

Where statutory late-payment interest applies, fixed compensation is £40, £70 or £100 according to the qualifying debt's size. Additional reasonable recovery costs are limited to the amount exceeding that compensation. These are not charges you make up.

The fixed sum comes from [section 5A of the Late Payment of Commercial Debts (Interest) Act 1998](<https://www.legislation.gov.uk/ukpga/1998/20/section/5A>). It depends on the size of the late payment. It is £40 for a payment under £1,000, £70 from £1,000 to less than £10,000, and £100 for £10,000 or more. It is a set amount per qualifying debt, not per part-payment or a percentage, and it comes on top of the interest.

If your real costs of recovering the payment are higher, you can also claim the reasonable difference. Keep the invoices for those costs, because a round figure is easy to refuse.

The catch is that the fixed sum only comes with statutory interest. If your contract has its own remedy for late payment that is substantial, statutory interest does not run, and nor does the fixed sum. Your contract's own interest clause then applies instead.

So read that clause before you add anything, and ask your solicitor if it is unclear which applies. Then list each late payment with its fixed sum and its interest, on separate lines of your demand.

To have every fixed sum, recovery cost and day of interest added to your demand, see our [Overdue payment recovery](<https://www.quantsurv.com/claims/overdue-payment-recovery>) service.

## Sources

1.  [Late Payment of Commercial Debts (Interest) Act 1998, s 5A (Compensation arising out of late payment)](<https://www.legislation.gov.uk/ukpga/1998/20/section/5A>). legislation.gov.uk.