# Is it illegal not to pay for construction work?

Failure to pay a properly due contract sum is usually a civil contractual or statutory issue, rather than automatically a criminal offence. The facts and available remedies matter.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## The answer

Failure to pay a properly due contract sum is usually a civil contractual or statutory issue, rather than automatically a criminal offence. The facts and available remedies matter. Do not confuse that distinction with an absence of legal rights or a conclusion about separate dishonest conduct.

First establish the obligation: the effective contract, application, notices, final date and payments. For an in-scope contract, a missing payer notice may engage [Housing Grants, Construction and Regeneration Act 1996, section 110B](<https://www.legislation.gov.uk/ukpga/1996/53/section/110B>), but only a qualifying application or properly given default notice establishes that route. Silence does not automatically make every invoice the notified sum. Check any valid pay less notice and the resulting unpaid balance.

Possible responses include a written demand, negotiation, adjudication or court proceedings. Statutory suspension under [section 112](<https://www.legislation.gov.uk/ukpga/1996/53/section/112>) requires its own conditions and at least seven days' compliant notice. Interest depends on a separate contractual or statutory basis. These are options to assess, not a compulsory demand–suspend–adjudicate sequence.

Consider live deadlines, the evidence, costs and collectability before choosing the route. An adjudication decision is generally binding pending final resolution, but payment and enforcement are not guaranteed. Obtain appropriate advice promptly if the payment position, suspension or formal proceedings are in issue.

[Overdue payment recovery](<https://www.quantsurv.com/claims/overdue-payment-recovery>) demands what is overdue with the interest the law allows, and organises the evidence for the next step you agree; formal proceedings need a separate representative.

## Sources

1.  [Housing Grants, Construction and Regeneration Act 1996, s 110B (Payment notices: payee’s notice in default of payer’s notice)](<https://www.legislation.gov.uk/ukpga/1996/53/section/110B>). legislation.gov.uk.
2.  [Housing Grants, Construction and Regeneration Act 1996, s 112 (Right to suspend performance for non-payment)](<https://www.legislation.gov.uk/ukpga/1996/53/section/112>). legislation.gov.uk.