# Does the Construction Act apply to my contract?

Part II of the Construction Act covers many construction agreements in England, Wales and Scotland, subject to exclusions. Northern Ireland has separate legislation. Check the operations, parties and applicable agreement.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## The answer

Part II of the Housing Grants, Construction and Regeneration Act 1996 covers many construction agreements in England, Wales and Scotland, subject to exclusions. Northern Ireland has separate legislation. Check the operations, parties and applicable agreement.

The Act is [the Housing Grants, Construction and Regeneration Act 1996](<https://www.legislation.gov.uk/ukpga/1996/53/part/II>), and our [guide to the Construction Act](<https://www.quantsurv.com/library/construction-act>) explains what it gives you. Whether it applies depends on the work, the parties, where the job is, when the contract was made and which legislation applies.

Some contracts are excluded. The best known is a contract with a homeowner for work on their own home, which [section 106](<https://www.legislation.gov.uk/ukpga/1996/53/section/106>) takes out of the Act's payment and adjudication rules. A subcontract between a trade subcontractor and a main contractor on a homeowner's project is not automatically excluded: check the parties to that particular agreement. Other exclusions need care too, as do mixed work and professional appointments.

Being outside the Act does not leave you with no rights. Your contract's own payment terms, any agreed dispute process and other legal protections still apply. So check where the work is, who each party is, what work is included, and what payment and dispute terms were agreed. Do that before you rely on a default notice or an adjudication timetable.

For work on your own home, check the residential-occupier exception against the actual parties and use of the dwelling. Private ownership alone is not the test.

Section 106 concerns a contract with a residential occupier for work principally relating to a dwelling they occupy or intend to occupy as their residence.

A development business constructing homes for sale should not assume that exception applies merely because the buildings are residential. A contractor’s separate subcontract also needs its own assessment.

Outside the statutory regime, an express contractual adjudication or payment mechanism may still apply. Check its wording and enforceability rather than importing the Scheme automatically.

To have your contracts read for when you will be paid and where the Construction Act fills the gaps, see our [Payment timetable and notice process setup](<https://www.quantsurv.com/claims#client-types>) service.

## Sources

1.  [Housing Grants, Construction and Regeneration Act 1996, Part II (Construction contracts), as amended by the Local Democracy, Economic Development and Construction Act 2009, Part 8](<https://www.legislation.gov.uk/ukpga/1996/53/part/II>). legislation.gov.uk.
2.  [Housing Grants, Construction and Regeneration Act 1996, s 106 (Provisions not applicable to contract with residential occupier)](<https://www.legislation.gov.uk/ukpga/1996/53/section/106>). legislation.gov.uk.

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)

[Browse the Library](<https://www.quantsurv.com/library>)