# Are pay when paid clauses enforceable?

Usually not: the Construction Act makes pay-when-paid clauses ineffective, but there is an exception for insolvency further up the chain.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 9 October 2026 · About 2 min readShare

## The answer

Usually not: the Housing Grants, Construction and Regeneration Act 1996 makes pay-when-paid clauses ineffective, but there is an exception for insolvency further up the chain.

[Section 113 of the Housing Grants, Construction and Regeneration Act 1996](<https://www.legislation.gov.uk/ukpga/1996/53/section/113>) deals with clauses that make your payment depend on the payer being paid. It prohibits them, except in the insolvency circumstances it allows. Where a clause fails, a fallback payment rule may be needed to fill the gap.

Whether your clause is caught depends on what it actually makes payment depend on, which contracts and parties are involved, and whether the Act covers your contract. An upstream performance or certification condition needs a separate check under [section 110(1A)–(1B)](<https://www.legislation.gov.uk/ukpga/1996/53/section/110>); section 113 concerns actual payment further up the chain. A delayed certificate or unpaid invoice alone does not establish the answer.

So read the clause, set out the dates and the payment record, and note any evidence of insolvency. Then send the question of the clause's legal effect to your solicitor. A commercial review can set out the dates and evidence in the meantime.

### Keep the payment explanation and documents

Save the payer's explanation of why payment is being withheld, along with the actual clause relied on. Check the payment notices and the cycle independently.

Use the [payment dates calculator](<https://www.quantsurv.com/library/tools/payment-dates-calculator>) to organise the relevant dates. If insolvency is raised, establish whose insolvency is alleged and obtain advice on the actual exception and contract wording before assuming the clause is ineffective.

[Payment timetable and notice process setup](<https://www.quantsurv.com/claims#client-types>) finds the conditional payment clauses in your contracts and sets out what to do about each.

## Sources

1.  [Housing Grants, Construction and Regeneration Act 1996, s 113 (Prohibition of conditional payment provisions)](<https://www.legislation.gov.uk/ukpga/1996/53/section/113>). legislation.gov.uk.
2.  [Housing Grants, Construction and Regeneration Act 1996, s 110 (Dates for payment)](<https://www.legislation.gov.uk/ukpga/1996/53/section/110>). legislation.gov.uk.

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)

[Browse the Library](<https://www.quantsurv.com/library>)