# Read a letter of intent like a contract and track its cap

Read the letter's actual scope, cap, expiry, valuation and payment terms before starting. Track commitments as well as expenditure and seek written authority before crossing a limit.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 9 October 2026 · About 2 min readShare

## Why

A letter of intent may authorise limited early work while a contract is negotiated, but its legal effect depends on its wording and subsequent agreement or conduct. A cap, expiry and scope limit can raise different issues. Do not assume work beyond any of them is authorised or automatically unpaid: record the exposure and obtain a decision before committing further resources.

## How do I do it?

1.  Read the letter with the same checklist you use for a full contract. Cover the scope, sum, cap, price basis, payment terms, what happens at the cap and how it ends.
2.  Put the cap in your cost system as a hard limit, with a warning at 75 per cent. Tell the site team the figure.
3.  Put the letter's expiry date in the diary, with the date you will chase the contract if it has not arrived.
4.  Write before you reach the cap, asking for it to be raised or the contract signed. Keep the reply with the letter.

Our [Letter-of-intent controls setup](<https://www.quantsurv.com/claims#client-types>) establishes a way to track the authority, expiry and spending limit stated in the letter.

If the work has already run past the letter, see [how work beyond a letter of intent is valued and recovered](<https://www.quantsurv.com/claims/payment-recovery-without-a-signed-contract>).