# Build a dated chronology before you argue what was agreed

When a job has run past its paper, or never had any, a dated chronology shows who agreed what and when, from the documents. Put every document in date order, mark scope limits, caps, expiry dates and subsequent instructions, then value the work under the alternative contractual positions.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## Why

Once work has run past a letter of intent, or started on a quote and a phone call, memories split. Each side remembers a different price, scope and start date. The argument drifts between what was said, what was built and what was paid, and every point is made from memory. A chronology built from the originals ends that drift. It shows which document says what and where the authority or terms become disputed. It also shows which part of the money is unpaid whichever side is right. You can claim that part now and argue the rest on the documents, not on recollection. Whether a contract was formed, and on whose terms, is a question for your solicitor. The chronology is the first thing they will ask for.

## How do I do it?

1.  Gather the originals: the quote, any letter of intent or order, emails and messages, instructions, the drawings you built from, invoices and payments.
2.  Put them in one list in date order, each with its date, its sender and what it says about scope, price or payment.
3.  Mark each entry as agreed, one side's version or in dispute, and attach each disputed term to the message it came from.
4.  Record separately when a cap was reached, an expiry occurred and later instructions were issued. These are evidence for contractual or legal assessment, not necessarily a single date on which all terms stopped applying.
5.  Value the work on each side of that line and reconcile both against every payment. The sum unpaid on either reading is then plain.

Our [Payment recovery without a signed contract](<https://www.quantsurv.com/claims/payment-recovery-without-a-signed-contract>) uses this chronology to organise the valuation evidence, with legal advice on disputed formation or entitlement.