# I've gone past the letter of intent's cap

The letter capped what we could spend, the job carried on, and now they say the cap is all we get.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

The cap in a letter of intent is easy to pass. Nobody on site knows the figure. The other party keeps issuing instructions, and the contract meant to replace the letter is still being negotiated. By the time anyone checks, the work done is worth well over the cap.

Then it points at the cap and says that is all you are owed. Whether it is right depends first on the letter's wording. It also turns on whether the cap was later raised or replaced by a fuller agreement. And it turns on what was said and done as the work went on. Those are questions for your solicitor, not for a site argument. Preserve the evidence and obtain advice promptly; leaving the issue unresolved can make the position harder to establish.

What does not depend on the legal answer is the value of the work: what was built, what it cost and what has been paid. You can measure and prove that now, while the records and the people are still there.

## What do I need to do?

1.  Measure the work and separate the periods and commitments inside and beyond the letter's cap.
2.  Identify the applicable valuation basis and support quantities, rates or costs with records; actual cost is not automatically the price.
3.  Gather later instructions, payments and correspondence about extending or replacing the letter.
4.  Have the legal effect checked, then reconcile the supported valuation against payments and set out the balance and remaining uncertainty.

To have this done for you, see our [Payment recovery without a signed contract](<https://www.quantsurv.com/claims/payment-recovery-without-a-signed-contract>) and [Letter-of-intent controls setup](<https://www.quantsurv.com/claims#client-types>) services.