# My letter of intent has expired and I'm still working

The letter ran out weeks ago, the contract still isn't signed, and nobody has said anything.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

A letter of intent may authorise limited early work while the contract is negotiated. Its actual scope, cap and expiry come from its wording. Then the negotiation stalls, the job does not, and the expiry date passes with your gangs still on site. Nothing changes on the day, so nobody notices.

What changes is the paper behind the work. Work after the expiry may still fall under the letter. It may fall under a contract formed some other way, or under no contract at all. Which applies depends on the wording and on what happens next, and each answer values and pays the work differently.

That is a legal question, and it is easier to answer while the facts are fresh. Every week you work past the date adds to the sum riding on the answer. The commercial steps do not have to wait for it.

## What do I need to do?

1.  Request a written extension with an adequate cap or completion of the full contract.
2.  Record work and commitments after expiry separately from those authorised by the original letter.
3.  Value the work done and reconcile payments, keeping the assumptions and alternative positions visible.
4.  Take advice on the continuing agreement and obligations before deciding whether to proceed, suspend or stop.

To have this done for you, see our [Letter-of-intent controls setup](<https://www.quantsurv.com/claims#client-types>) and [Payment recovery without a signed contract](<https://www.quantsurv.com/claims/payment-recovery-without-a-signed-contract>) services.