# Support a delay notice with the required detail

After a delay notice, provide the particulars and updates your contract requires. Explain how the event affects the relevant completion date.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 1 min readShare

## Why

A notice alone may not contain enough information to assess time. Avoid assuming that every day of disruption moves completion by a day; programme logic and other causes can matter.

## How do I do it?

1.  Identify the event, contractual basis and affected work.
2.  Link its timing to the programme and contemporaneous records.
3.  Submit the required particulars and updates, seeking a planner’s input where the analysis needs it.

Our [Construction contract management](<https://www.quantsurv.com/quantity-surveying#client-types>) keeps notices, supporting details and programme records aligned with the contract procedure.

[Browse delay and disruption in the Library](<https://www.quantsurv.com/library#topic-delay>)

[Browse the Library](<https://www.quantsurv.com/library>)