# What is an extension of time (EOT) in a contract?

An extension of time, or EOT, moves your completion date later for a delay your contract lists as grounds for more time.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## The answer

An extension of time, or EOT, moves your completion date later for a delay your contract lists as grounds for more time. Delay damages are then counted from the new date, not the original one.

A useful EOT submission connects the qualifying event with its effect on contractual completion. Notices and records support that analysis; paperwork alone does not establish how much time is due.

First, notify the delay once it becomes apparent, in the form and to the person your contract names. Then send particulars: the cause, the dates, the work affected and your estimate of the effect on your completion date. Update them as things change, and keep the records that prove each one. Some contracts make the notice a condition of any extension, so a late notice can lose the time altogether.

An EOT gives you time, not money. The cost of the delay is claimed separately, as loss and expense or by whatever route your contract gives. Overlapping delays need analysis of their effects and the contract's allocation of risk; time and money may have different outcomes. How many days an event is worth is for a programming expert. Completion-date and notice tracking setup sets up the notices and records that get the extension decided.

For a tested notice and supporting-record routine, [Completion-date and notice tracking setup](<https://www.quantsurv.com/claims#client-types>) service.

[Browse delay and disruption in the Library](<https://www.quantsurv.com/library#topic-delay>)

[Browse the Library](<https://www.quantsurv.com/library>)