# What are liquidated damages (LADs) in a contract?

Liquidated damages, or LADs, are a fixed sum for each day or week you finish late, agreed in the contract before work starts.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## The answer

Liquidated damages, or LADs, are a fixed sum for each day or week you finish late, agreed in the contract before work starts. Delay damages is a wider description that may include either an agreed rate or a claim for proven loss.

LAD stands for liquidated and ascertained damages. The rate takes the place of proof: the other party does not have to show what your late finish cost it.

Distinguish a liquidated-damages rate in your contract from a main contractor's claim for actual delay loss. The latter requires its own contractual basis, causation and evidence of loss; an upstream deduction is not automatically your liability. Check the relevant completion date as extended and the period for which liability is alleged.

So before you sign, find the rate, any cap and the notices the clause needs. Once work starts, send a delay notice every time others hold you up. If a charge lands, check the rate, the weeks and the notices before you argue about the delay.

To have a liquidated damages charge tested against your contract and extensions, see our [Delay damages review and response](<https://www.quantsurv.com/claims/delay-damages-review-and-response>) service.

[Browse delay and disruption in the Library](<https://www.quantsurv.com/library#topic-delay>)

[Browse the Library](<https://www.quantsurv.com/library>)