# Can the other party take delay damages without a non-completion certificate?

Not if your contract makes a certificate or notice of non-completion a condition of the charge, and many do.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## The answer

Check whether your actual contract makes a certificate, non-completion notice or another communication a condition of delay damages. Read the selected form, edition, options and amendments rather than importing a main-contract checklist.

Some JCT main-contract forms use a non-completion certificate and further notice steps. JCT subcontracts may instead require a notice from the main contractor, with different conditions. NEC delay damages depend on the applicable option and amended assessment provisions. The effect of a later extension, takeover or revised completion date must also be checked under that actual wording.

Make a checklist of each required step, its authorised sender, recipient, content and service timing. Separate those conditions from payment-notice requirements. A valid pay less notice does not necessarily cure a missing prerequisite to the underlying damages, while a disputed damages entitlement does not itself invalidate every payment notice.

Have the representative assess the legal consequence of any missing step. Recalculate from the operative dates and maintain a clear distinction between the claimed liability and the amount payable in the particular payment cycle.

To have every step behind a delay damages charge checked, and the deduction challenged where one is missing, see our [Delay damages review and response](<https://www.quantsurv.com/claims/delay-damages-review-and-response>) service.