# Are liquidated damages enforceable?

Enforceability depends on the clause and legal context. Separately check whether the particular deduction meets the contract's conditions and calculation rules.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## The answer

Enforceability depends on the clause and legal context. In [Cavendish and ParkingEye, \[2015\] UKSC 67](<https://www.supremecourt.uk/cases/uksc-2013-0280>), the Supreme Court considered whether a secondary obligation imposed a detriment disproportionate to the innocent party's legitimate interest in performance. The test is not simply whether the amount equals a forecast of financial loss. Ask your solicitor to apply the relevant law to the actual clause and circumstances.

A stated rate does not itself prove that a particular deduction is due. Check the operative completion or section dates, extensions applied for and granted, required notices, rate, counting rule, caps, takeover provisions and the evidence of delay. Establish what any liability cap actually covers rather than assuming the delay-damages rate caps all liability.

Before agreeing to delete or replace the clause, compare the alternative exposure. General damages or another contractual route may remain, depending on the agreement and law. The enforceability question and the evidence supporting this particular charge should both be assessed.

Our [Delay damages review and response](<https://www.quantsurv.com/claims/delay-damages-review-and-response>) service tests a deduction like this once it has been made.