# Can they take liquidated damages without a pay less notice?

No, not from a sum already notified as due: to pay less than that, the other party must give a pay less notice in time.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## The answer

No, not from a sum already notified as due: to pay less than that, the other party must give a pay less notice in time. Liquidated damages are no exception.

The rule is in [section 111 of the Housing Grants, Construction and Regeneration Act 1996](<https://www.legislation.gov.uk/ukpga/1996/53/section/111n1>). The other party must pay the notified sum by the final date for payment, unless it has given a pay less notice. That notice must be given within the period the contract sets before that date. It must state the sum the other party considers due and how it was worked out.

So check which notice carried the deduction. If the other party's own payment notice already showed the damages and how they were worked out, the notified sum is the lower figure. If the notified sum is your application, or a payment notice that did not show them, a pay less notice in time was needed.

Your contract may also require its own notices before damages can be deducted at all. A missing notice decides that payment cycle, not whether damages are due in the end. That can still be argued in a later cycle or in the final account.

Our [Delay damages review and response](<https://www.quantsurv.com/claims/delay-damages-review-and-response>) service tests the notices behind a deduction as well as the arithmetic.

## Sources

1.  [Housing Grants, Construction and Regeneration Act 1996, s 111 (Requirement to pay notified sum)](<https://www.legislation.gov.uk/ukpga/1996/53/section/111n1>). legislation.gov.uk.

[Browse delay and disruption in the Library](<https://www.quantsurv.com/library#topic-delay>)

[Browse the Library](<https://www.quantsurv.com/library>)