# Work and property inventory

Record the work, materials, plant and documents present at a defined handover or termination date.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>) · About 2 min readShare

## How to use it

Inspect and photograph the position at the stated cutoff. Record ownership evidence and disagreements; possession alone does not establish title.

### Work and property inventory

Inspect and photograph the position at the stated cutoff. Record ownership evidence and disagreements; possession alone does not establish title.

[Download blank Excel workbook](<https://www.quantsurv.com/downloads/library/work-and-property-inventory.xlsx>)

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

#### Work and property inventory

Scroll across if needed to read the whole record. A dash means no value has been entered.

Work and property inventory: completed fictional example
| Reference / location | Item / work status | Quantity | Claimed owner | Evidence | Condition / next action |
| --- | --- | --- | --- | --- | --- |
| INV-01 / Level 1 | Completed partition work | 120 | Work incorporated in project | Drawing mark-up M-14; photos P-1401 | Measure jointly; payment status separate |
| INV-02 / store | Unfixed board sheets | 40 | Westhaven Interiors, subject to contract | Invoice I-18; delivery DN-18 | Dry and undamaged; title provision to check |
| INV-03 / Level 2 | Mobile tower T1 | 1 | Hire company | Hire H-17 | Arrange agreed collection; retain receipt |

Example cutoff: 14 October 2026 at 16:00. Preserve access records and avoid removing disputed property without resolving the relevant rights.

## Understanding your results

Example cutoff: 14 October 2026 at 16:00. Preserve access records and avoid removing disputed property without resolving the relevant rights.

## How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the [related guidance](<https://www.quantsurv.com/termination/tips/record-the-termination-day>) for the context and checks behind this template.