# Weekly commercial review record

Record the payment, change, programme and close-out decisions from a weekly commercial review.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>) · About 2 min readShare

## How to use it

Use this as the meeting record and link actions to the live registers. State who decided what and what remains unresolved.

### Weekly commercial review record

Use this as the meeting record and link actions to the live registers. State who decided what and what remains unresolved.

[Download blank Word template](<https://www.quantsurv.com/downloads/library/weekly-commercial-review-record.docx>)

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

#### Weekly commercial review record

Scroll across if needed to read the whole record. A dash means no value has been entered.

Weekly commercial review record: completed fictional example
| Review item | Position at 14 Oct 2026 | Decision / action | Owner | Due |
| --- | --- | --- | --- | --- |
| Cash | September assessment £22,000; £20,000 received | Chase £2,000 and reconcile bank receipt | Accounts lead | 16 Oct |
| Changes | CH-07 £3,200 submitted; no agreement | Complete evidence and seek written assessment | QS | 16 Oct |
| Programme | Level 1 access affected 7–8 Oct | Preserve baseline and update; assess completion effect | Planner | 15 Oct |
| Close-out | Handover record HR-01 complete | Obtain as-built drawing before package completion | Design lead | 16 Oct |

The completed example uses fictional people, events and records. Replace it with your own verified information and preserve supporting evidence.

## Understanding your results

The completed example uses fictional people, events and records. Replace it with your own verified information and preserve supporting evidence.

## How it works

The Word file provides an unpopulated working structure to complete for your project. The completed fictional example stays on this page.

Read the [related guidance](<https://www.quantsurv.com/delay-and-disruption/problems/system-fades>) for the context and checks behind this template.

If you need help preparing or reviewing the project records, our [quantity surveying services](<https://www.quantsurv.com/quantity-surveying>) explain the tasks available under a separate appointment. Agree the deliverable, responsibilities and required specialist input before work starts.