# Variation register template

Follow each change from instruction through notice, valuation and payment application without losing its supporting records.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>) · About 3 min readShare

## How to use it

Give each change a stable reference. Keep the instruction, required notices, valuation and application reference together.

A register records what happened. It does not turn an unauthorised instruction into an entitlement or replace notice requirements in your contract.

### Variation register

Keep stable references from instruction through valuation and application. Amounts exclude VAT.

[Download blank Excel workbook](<https://www.quantsurv.com/downloads/claims/variation-register-template.xlsx>)

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

#### Variation register

Scroll across if needed to read the whole record. A dash means no value has been entered.

Variation register: completed fictional example
| Variation ref | Change description | Instruction / date / authority | Notice / date / service proof | Valuation evidence | Claimed value (£) | Assessed value (£) | Difference (£) | Application ref / date | Status / next action |
| --- | --- | --- | --- | --- | --- | --- | --- | --- | --- |
| V-001 | Additional partitions, Level 2 | SI-17 / 2026-09-01 / authority checked | N-17 / 2026-09-02 / receipt retained | Drawing rev C; quantities Q17; agreed rates | £6,000.00 | £4,200.00 | £1,800.00 | APP-06 / 2026-09-20 | Request explanation of excluded quantities |
| V-002 | Revised door ironmongery | SI-19 / 2026-09-05 / authority checked | N-19 / 2026-09-06 / receipt retained | Supplier quotation SQ19; scope comparison | £2,500.00 | £2,500.00 | £0.00 | APP-06 / 2026-09-20 | Valuation agreed; trace payment separately |

Leave an absent assessment blank. This is a record, not a contractual notice. Reconcile actual payments separately.

## Understanding your results

Use the status and value columns to distinguish notified, priced, assessed and agreed changes. Check that instructions and evidence support each item. A register entry does not itself authorise work or establish an agreed valuation.

## How it works

-   Record what changed, who instructed it and the instruction date. Keep the original drawing, email or site instruction.
-   Check authority, confirmation requirements and notice deadlines against your contract. Record what you actually sent and retain proof of service.
-   Build the valuation from the applicable rates or evidenced cost. Link quantities, daywork sheets and invoices to the same reference.
-   Compare claimed and assessed values at the same date. Leave an absent assessment blank rather than entering an assumed zero.
-   Reconcile each item to the application and payment records. A valuation difference does not show the entire unpaid balance.

The fictional example records £6,000 claimed and £4,200 assessed for additional partitions, leaving a £1,800 valuation difference.

Our [Change valuation and compensation-event quotations](<https://www.quantsurv.com/quantity-surveying?service=%2Fquantity-surveying%2Fvariations-compensation-events#client-types>) service maintains the ordinary change record and valuation. An [Variation Recovery](<https://www.quantsurv.com/claims?service=%2Fvariations%2Fservices%2Fvariation-recovery#client-types>) examines disputed instructions, valuation and payment.