# Value engineering appraisal

Compare an alternative with the baseline across cost, quality, programme and approval requirements.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>) · About 2 min readShare

## How to use it

Evaluate equivalent performance and whole-project effects. Do not count a saving until the change and its consequential costs are understood.

### Value engineering appraisal

Evaluate equivalent performance and whole-project effects. Do not count a saving until the change and its consequential costs are understood.

[Download blank Excel workbook](<https://www.quantsurv.com/downloads/library/value-engineering-appraisal.xlsx>)

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

#### Value engineering appraisal

Scroll across if needed to read the whole record. A dash means no value has been entered.

Value engineering appraisal: completed fictional example
| Option | Baseline cost (£) | Alternative cost (£) | Consequential cost (£) | Net saving (£) | Performance / programme | Decision |
| --- | --- | --- | --- | --- | --- | --- |
| Alternative ceiling system | £18,000.00 | £15,000.00 | £1,000.00 | £2,000.00 | Same fire/acoustic rating subject to design approval; no time change | Proposed; designer review required |
| Standard door sizes | £12,000.00 | £10,500.00 | £500.00 | £1,000.00 | Layout adjustment required; lead time reduces one week | Client to approve revised layout |

The examples show £2,000 and £1,000 forecast savings before VAT. Include maintenance, warranty and performance consequences in the decision.

## Understanding your results

The examples show £2,000 and £1,000 forecast savings before VAT. Include maintenance, warranty and performance consequences in the decision.

## How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the [related guidance](<https://www.quantsurv.com/library/reduce-construction-cost>) for the context and checks behind this template.