# Site diary template

Record who worked where, what was achieved and what interrupted the work, with links to the original site evidence.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>) · About 2 min readShare

## How to use it

Complete daily while events are fresh. Include ordinary working days, unused resources and redeployment as well as interruptions.

### Site diary template

Complete daily while events are fresh. Include ordinary working days, unused resources and redeployment as well as interruptions.

[Download blank Excel workbook](<https://www.quantsurv.com/downloads/library/site-diary-template.xlsx>)

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

#### Site diary template

Scroll across if needed to read the whole record. A dash means no value has been entered.

Site diary template: completed fictional example
| Date / area | Planned work | Labour / plant | Actual output | Interruption / mitigation | Evidence / recorded by |
| --- | --- | --- | --- | --- | --- |
| 6 Oct 2026 / Level 1 | Install 40 m² partitions | 4 installers × 8 h; tower T1 | 40 m² installed | No interruption; normal access | Diary D-06; photos P-0601–04; A. Reed |
| 7 Oct 2026 / Level 1 | Install 40 m² partitions | 4 installers × 8 h; tower T1 | 20 m² installed | Access closed 08:00–12:00; 2 installers redeployed for 4 h | Diary D-07; access log AL-07; timesheets TS-07; A. Reed |

Keep factual observations separate from later explanations. An entry records events; it does not establish who is responsible for the cost.

## Understanding your results

Keep factual observations separate from later explanations. An entry records events; it does not establish who is responsible for the cost.

## How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the [related guidance](<https://www.quantsurv.com/delay-and-disruption/faq/what-should-a-diary-say>) for the context and checks behind this template.

If you need help preparing or reviewing the project records, our [quantity surveying services](<https://www.quantsurv.com/quantity-surveying>) explain the tasks available under a separate appointment. Agree the deliverable, responsibilities and required specialist input before work starts.

[Browse the Library](<https://www.quantsurv.com/library>)