# Settlement preparation record

Prepare an itemised settlement position and record precisely what is agreed, reserved or awaiting signed wording.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>) · About 2 min readShare

## How to use it

Use this to brief the negotiation and check the final document. Do not label an agreement complete until authority, scope and final wording are confirmed.

### Settlement preparation record

Use this to brief the negotiation and check the final document. Do not label an agreement complete until authority, scope and final wording are confirmed.

[Download blank Excel workbook](<https://www.quantsurv.com/downloads/library/settlement-preparation-record.xlsx>)

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

#### Settlement preparation record

Scroll across if needed to read the whole record. A dash means no value has been entered.

Settlement preparation record: completed fictional example
| Issue | Our position (£) | Other position (£) | Proposed compromise (£) | Scope / reservation | Status |
| --- | --- | --- | --- | --- | --- |
| CH-07 variation | £3,200.00 | £2,400.00 | £2,800.00 | This change only; time claim excluded | Agreed in principle; wording pending |
| Retention | £10,000.00 | £10,000.00 | £10,000.00 | Release remains subject to specified trigger | Not part of immediate payment |
| Legal wording | – | – | – | No general release beyond listed account items | Reviewer to check draft before signature |

A negotiation record is not a signed settlement agreement. Identify the parties, authority, payment conditions, tax treatment and claims being released.

## Understanding your results

A negotiation record is not a signed settlement agreement. Identify the parties, authority, payment conditions, tax treatment and claims being released.

## How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the [related guidance](<https://www.quantsurv.com/final-accounts/problems/settlement-no-plan>) for the context and checks behind this template.