# Risk and contingency register

Track identified risks and approved transfers from contingency without counting the same allowance twice.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>) · About 2 min readShare

## How to use it

Record risk owners and evidence for each transfer. Reconcile the revised base budget and remaining contingency to the approved total.

### Risk and contingency register

Record risk owners and evidence for each transfer. Reconcile the revised base budget and remaining contingency to the approved total.

[Download blank Excel workbook](<https://www.quantsurv.com/downloads/library/risk-and-contingency-register.xlsx>)

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

#### Risk register

Scroll across if needed to read the whole record. A dash means no value has been entered.

Risk register: completed fictional example
| Risk | Cause / effect | Allowance (£) | Owner | Mitigation / status |
| --- | --- | --- | --- | --- |
| R-01 ground conditions | Unknown local obstruction; additional excavation | £12,000.00 | Project lead | Trial pits before main works |
| R-02 design development | Unresolved service routes | £18,000.00 | Design lead | Coordinate before procurement |

#### Contingency control

Scroll across if needed to read the whole record. A dash means no value has been entered.

Contingency control: completed fictional example
| Budget | Original base (£) | Original contingency (£) | Approved transfer (£) | Revised base (£) | Remaining contingency (£) | Total (£) |
| --- | --- | --- | --- | --- | --- | --- |
| Approved project budget | £300,000.00 | £30,000.00 | £8,000.00 | £308,000.00 | £22,000.00 | £330,000.00 |

The £8,000 transfer reallocates the existing budget: £308,000 base plus £22,000 contingency still totals £330,000. It is not an extra saving or a new budget.

## Understanding your results

The £8,000 transfer reallocates the existing budget: £308,000 base plus £22,000 contingency still totals £330,000. It is not an extra saving or a new budget.

## How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the [related guidance](<https://www.quantsurv.com/library/construction-contingency>) for the context and checks behind this template.