# Rate build-up template

Build a unit rate from labour, material, plant and other priced inputs, with quantities and source references.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>) · About 2 min readShare

## How to use it

Use a consistent output unit. Record waste, productivity and the treatment of overhead and profit explicitly; keep supplier quotations dated.

### Rate build-up template

Use a consistent output unit. Record waste, productivity and the treatment of overhead and profit explicitly; keep supplier quotations dated.

[Download blank Excel workbook](<https://www.quantsurv.com/downloads/library/rate-build-up-template.xlsx>)

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

#### Rate build-up template

Scroll across if needed to read the whole record. A dash means no value has been entered.

Rate build-up template: completed fictional example
| Output / resource | Quantity per output unit | Input unit | Unit cost (£) | Cost per output (£) | Source / assumption |
| --- | --- | --- | --- | --- | --- |
| 1 m² partition / labour | 0.75 | hour | £30.00 | £22.50 | Labour cost L-01; assumed productivity 0.75 h/m² |
| 1 m² partition / board | 2.1 | m² | £8.00 | £16.80 | Supplier Q-14; includes 5% board waste |
| 1 m² partition / framing and fixings | 1 | set | £10.00 | £10.00 | Supplier Q-15 |
| 1 m² partition / plant allowance | 1 | m² | £1.70 | £1.70 | Hire allocation H-01 |

The example direct rate is £51.00/m² excluding VAT, overhead and profit. Add those separately where the pricing basis permits.

## Understanding your results

The example direct rate is £51.00/m² excluding VAT, overhead and profit. Add those separately where the pricing basis permits.

## How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the [related guidance](<https://www.quantsurv.com/delay-and-disruption/tips/source-every-rate>) for the context and checks behind this template.