# Project budget and cost plan

Build a project budget by element and keep construction cost, fees, risk allowances and tax assumptions visible.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>) · About 3 min readShare

## How to use it

Replace the fictional allowances with quantities, quotations and local project information. Use one project scenario at a time and confirm VAT treatment separately.

### Project budget and cost plan

Replace the fictional allowances with quantities, quotations and local project information. Use one project scenario at a time and confirm VAT treatment separately.

[Download blank Excel workbook](<https://www.quantsurv.com/downloads/library/project-budget-and-cost-plan.xlsx>)

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

#### Extension budget

Scroll across if needed to read the whole record. A dash means no value has been entered.

Extension budget: completed fictional example
| Element | Quantity | Unit | Rate (£) | Allowance (£) | Basis / exclusion |
| --- | --- | --- | --- | --- | --- |
| Groundworks | 1 | allowance | £18,000.00 | £18,000.00 | Normal foundations assumed; ground risk separate |
| Structure and envelope | 40 | m² | £1,500.00 | £60,000.00 | Fictional 40 m² extension; no benchmark claim |
| Services and finishes | 40 | m² | £800.00 | £32,000.00 | Agreed domestic specification |
| Fees and approvals | 1 | allowance | £12,000.00 | £12,000.00 | Design and approvals estimate |
| Risk allowance | 1 | allowance | £12,000.00 | £12,000.00 | Client allowance; release by decision |

#### Other project scenarios

Scroll across if needed to read the whole record. A dash means no value has been entered.

Other project scenarios: completed fictional example
| Scenario | Construction (£) | Fees (£) | Risk (£) | Budget before VAT (£) | Scope assumption |
| --- | --- | --- | --- | --- | --- |
| Renovation | £120,000.00 | £15,000.00 | £18,000.00 | £153,000.00 | Existing house; no major structural replacement |
| Office fit-out | £220,000.00 | £25,000.00 | £22,000.00 | £267,000.00 | Internal fit-out; lease and landlord works excluded |

These are invented teaching allowances, not current market rates or project quotations. Add the correct project-specific tax, land, finance and client costs before setting a funding requirement.

## Understanding your results

These are invented teaching allowances, not current market rates or project quotations. Add the correct project-specific tax, land, finance and client costs before setting a funding requirement.

## How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the [related guidance](<https://www.quantsurv.com/library/estimate-vs-cost-plan>) for the context and checks behind this template.