# Payment notice review record

Review a received payment notice through separate procedure, valuation and evidence checks.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>) · About 2 min readShare

## How to use it

Preserve the original notice first. Record doubts as unresolved questions and obtain the actual contract timetable before drawing conclusions.

### Payment notice review record

Preserve the original notice first. Record doubts as unresolved questions and obtain the actual contract timetable before drawing conclusions.

[Download blank Excel workbook](<https://www.quantsurv.com/downloads/library/payment-notice-review-record.xlsx>)

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

#### Payment notice review record

Scroll across if needed to read the whole record. A dash means no value has been entered.

Payment notice review record: completed fictional example
| Review area | Received record / position | Evidence | Conclusion / action |
| --- | --- | --- | --- |
| Identity and cycle | PN-09 from named payer; September cycle | Original email and signed order | Identity checked |
| Timing and service | Received 25 Sep 15:08 | Receipt plus payment schedule P rev 2 | Deadline calculation requires reviewer sign-off |
| Amount and basis | £22,000 assessed against £24,000 application | PN-09 and APP-09 | £2,000 measurement difference unexplained |
| Action | Request breakdown; retain challenge dates | Clarification email C-09 | No conclusion on validity solely from arithmetic |

The record separates documentary checks from legal conclusions. An unexplained difference is not automatically an invalid notice.

## Understanding your results

The record separates documentary checks from legal conclusions. An unexplained difference is not automatically an invalid notice.

## How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the [related guidance](<https://www.quantsurv.com/underpaid/tips/check-the-pay-less-notice>) for the context and checks behind this template.