# Payment notice preparation examples

Compare a payer’s payment notice with a payee’s default-notice preparation record, including the calculation and timing questions.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>) · About 3 min readShare

## How to use it

Identify which notice mechanism applies before using either illustration. A prior compliant application may affect whether another default notice can be given.

### Payment notice preparation examples

Identify which notice mechanism applies before using either illustration. A prior compliant application may affect whether another default notice can be given.

[Download blank Word template](<https://www.quantsurv.com/downloads/library/payment-notice-preparation-examples.docx>)

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

#### Payer payment notice illustration

Scroll across if needed to read the whole record. A dash means no value has been entered.

Payer payment notice illustration: completed fictional example
| Field | Completed fictional record |
| --- | --- |
| Parties / contract | Alder Mere Projects to Westhaven Interiors; WH-042 |
| Cycle / due date | September payment; due date 23 Sep 2026 in the fictional contract |
| Issue | 25 Sep 2026 through the agreed notice route |
| Sum considered due at due date | £22,000 excluding VAT |
| Calculation basis | £120,000 cumulative assessed work less £6,000 retention and £92,000 previous assessed payments |
| Evidence | PN-09 with measured assessment MA-09 and retention reconciliation; receipt retained |

#### Payee default-notice preparation illustration

Scroll across if needed to read the whole record. A dash means no value has been entered.

Payee default-notice preparation illustration: completed fictional example
| Field | Completed fictional record |
| --- | --- |
| Separate scenario | Assume required payer notice was not issued; do not combine with the payer-notice scenario above |
| Initial check | Confirm whether a prior application already operates as the relevant notice under the applicable rules |
| Proposed sum and basis | £24,000: £120,000 gross less £6,000 retention and £90,000 prior assessment |
| Timing | Record the missed notice deadline and actual issue date; check any resulting postponement of final payment |
| Draft and service | Prepare only after mechanism is verified; retain calculation, issued version and service proof |

The second illustration is a preparation record, not ready-to-serve wording. The contract and applicable law determine which notice is available and its effect on payment dates.

-   [Construction Act payment notice provisions, as inserted in 2009](<https://www.legislation.gov.uk/ukpga/2009/20/pdfs/ukpga_20090020_en.pdf>)

## Understanding your results

The second illustration is a preparation record, not ready-to-serve wording. The contract and applicable law determine which notice is available and its effect on payment dates.

## How it works

The Word file provides an unpopulated working structure to complete for your project. The completed fictional example stays on this page.

Read the [related guidance](<https://www.quantsurv.com/underpaid/faq/what-must-a-payment-notice-include>) for the context and checks behind this template.