# Payment document index

Keep the issued application, incoming notices and proof of service together for each payment cycle.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>) · About 2 min readShare

## How to use it

Record immutable issued versions and their locations. Do not replace an issued file with a later draft.

### Payment document index

Record immutable issued versions and their locations. Do not replace an issued file with a later draft.

[Download blank Excel workbook](<https://www.quantsurv.com/downloads/library/payment-document-index.xlsx>)

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

#### Payment document index

Scroll across if needed to read the whole record. A dash means no value has been entered.

Payment document index: completed fictional example
| Cycle / reference | Document / revision | Issued / received | File location | Delivery proof | Purpose / status |
| --- | --- | --- | --- | --- | --- |
| September / APP-09 | Application r1 | 20 Sep 2026 10:12 | /payments/09/APP-09-r1.xlsx | Portal R-091 | £24,000 application |
| September / PN-09 | Assessment notice r1 | 25 Sep 2026 15:08 | /payments/09/PN-09.pdf | Original received email | £22,000 assessment; £2,000 difference |
| September / B-17 | Bank receipt record | 16 Oct 2026 | /payments/09/B-17.pdf | Bank statement | £20,000 allocated; £2,000 assessed balance |

The completed example uses fictional people, events and records. Replace it with your own verified information and preserve supporting evidence.

## Understanding your results

The completed example uses fictional people, events and records. Replace it with your own verified information and preserve supporting evidence.

## How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the [related guidance](<https://www.quantsurv.com/underpaid/tips/one-folder-per-cycle>) for the context and checks behind this template.

If you need help preparing or reviewing the project records, our [quantity surveying services](<https://www.quantsurv.com/quantity-surveying>) explain the tasks available under a separate appointment. Agree the deliverable, responsibilities and required specialist input before work starts.