# Payment application template

Prepare a cumulative interim valuation showing work, changes, retention, prior assessments and the current amount requested.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>) · About 2 min readShare

## How to use it

Measure at the agreed valuation date. Use the contract valuation and retention rules, then reconcile the current application to earlier assessments.

### Payment application template

Measure at the agreed valuation date. Use the contract valuation and retention rules, then reconcile the current application to earlier assessments.

[Download blank Excel workbook](<https://www.quantsurv.com/downloads/library/payment-application-template.xlsx>)

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

#### Valuation detail

Scroll across if needed to read the whole record. A dash means no value has been entered.

Valuation detail: completed fictional example
| Item | Description | Cumulative value (£) | Supporting record |
| --- | --- | --- | --- |
| MW-01 | Measured original work | £110,000.00 | Measure MW-10; drawing P-104 C |
| CH-08 | Agreed additional work | £10,000.00 | Change agreement A-08 |

#### Application summary

Scroll across if needed to read the whole record. A dash means no value has been entered.

Application summary: completed fictional example
| Cycle / valuation date | Gross cumulative (£) | Retention (£) | Previous assessed (£) | Current application (£) | VAT / payment basis |
| --- | --- | --- | --- | --- | --- |
| October / 20 Oct 2026 | £120,000.00 | £6,000.00 | £90,000.00 | £24,000.00 | Excluding VAT; check invoice and tax treatment separately |

Example retention is £6,000 on £120,000. Previous assessed payments of £90,000 are not the same as cash received. Review the separate cash reconciliation before chasing payment.

## Understanding your results

Example retention is £6,000 on £120,000. Previous assessed payments of £90,000 are not the same as cash received. Review the separate cash reconciliation before chasing payment.

## How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the [related guidance](<https://www.quantsurv.com/library/interim-valuations-payment-applications>) for the context and checks behind this template.

If you need help preparing or reviewing the project records, our [quantity surveying services](<https://www.quantsurv.com/quantity-surveying>) explain the tasks available under a separate appointment. Agree the deliverable, responsibilities and required specialist input before work starts.

[Browse the Library](<https://www.quantsurv.com/library>)