# Pay less notice drafting sheet

See a completed payment-cycle illustration and the calculation, contract checks and service record behind it.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>) · About 3 min readShare

## How to use it

Complete the contract and timing checks before drafting. Replace the fictional amounts, reasons and references with a fully supported calculation for the actual payment.

### Pay less notice drafting sheet

Complete the contract and timing checks before drafting. Replace the fictional amounts, reasons and references with a fully supported calculation for the actual payment.

[Download blank Word template](<https://www.quantsurv.com/downloads/library/pay-less-notice-drafting-sheet.docx>)

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

#### Notice details

Project / contract

Westhaven refurbishment; fictional order WH-042

Payer / sender

Alder Mere Projects Ltd, authorised commercial lead

Payee / recipient

Westhaven Interiors Ltd, contractual notice recipient

Payment cycle

October 2026; application APP-10

Notice date

27 October 2026

Final date for payment

16 November 2026, from agreed schedule P rev 2

#### Notice of intention to pay less

For the identified payment, the payer considers £164,000 excluding VAT to be due at the date this notice is given. The basis is the notified sum of £180,000, less the £11,000 valuation adjustment and £5,000 retention explained below.

The £11,000 adjustment removes work not completed at the valuation date, identified in measurement review MR-10 items 1 to 4. The £5,000 retention is calculated under the agreed retention schedule and reconciliation RR-10. Both schedules accompany this illustration.

This is fictional original wording for study. The actual notice must satisfy the applicable contract and statutory requirements, including timing, content, authority and service.

#### Calculation supplied with the notice

Scroll across if needed to read the whole record. A dash means no value has been entered.

Calculation supplied with the notice: completed fictional example
| Item | Amount (£) | Basis / evidence |
| --- | --- | --- |
| Notified sum | £180,000.00 | APP-10; identify the operative notice for the real payment |
| Valuation adjustment | \-£11,000.00 | MR-10 items 1 to 4: uncompleted work |
| Retention | \-£5,000.00 | RR-10; contractual basis and prior retention reconciled |
| Sum considered due | £164,000.00 | 180,000 - 11,000 - 5,000 |

#### Preparation and delivery checks

Scroll across if needed to read the whole record. A dash means no value has been entered.

Preparation and delivery checks: completed fictional example
| Check | Completed fictional record |
| --- | --- |
| Deadline | Project-specific schedule P rev 2 checked: latest service 9 Nov 2026; issued 27 Oct |
| Recipient / method | Named notice recipient through the agreed portal route |
| Issued version and receipt | PLN-10 r1 with MR-10 and RR-10; portal receipt R-271 retained |

The dates are an expressly invented project timetable, not a default notice period. A calculation alone does not prove a notice valid or establish entitlement to deduct.

-   [Construction Act payment notice provisions, as inserted in 2009](<https://www.legislation.gov.uk/ukpga/2009/20/pdfs/ukpga_20090020_en.pdf>)

## Understanding your results

The dates are an expressly invented project timetable, not a default notice period. A calculation alone does not prove a notice valid or establish entitlement to deduct.

## How it works

The Word file provides an unpopulated working structure to complete for your project. The completed fictional example stays on this page.

Read the [related guidance](<https://www.quantsurv.com/underpaid/faq/what-does-a-pay-less-notice-look-like>) for the context and checks behind this template.