# Notice and action diary

Track each contract deadline from its trigger to its checked date, responsible person and evidence of delivery.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>) · About 2 min readShare

## How to use it

Enter the actual contract rule and trigger; have the resulting deadline checked. This diary does not calculate legal deadlines or assume a standard notice period.

### Notice and action diary

Enter the actual contract rule and trigger; have the resulting deadline checked. This diary does not calculate legal deadlines or assume a standard notice period.

[Download blank Excel workbook](<https://www.quantsurv.com/downloads/library/notice-and-action-diary.xlsx>)

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

#### Notice and action diary

Scroll across if needed to read the whole record. A dash means no value has been entered.

Notice and action diary: completed fictional example
| Reference / action | Trigger and source | Verified deadline | Owner / deputy | Delivery route | Issued / proof | Status |
| --- | --- | --- | --- | --- | --- | --- |
| N-01: change notice | Instruction I-07 received 7 Oct; agreed project diary D-02 | 9 Oct 2026, 16:00 | Commercial lead / project lead | Contract portal, notice category | 8 Oct 14:30; receipt R-008 | Delivered; response pending |
| PAY-01: application | Schedule P rev 2, October cycle | 20 Oct 2026, 12:00 | QS / accounts lead | Named accounts inbox plus portal | Not yet issued | Draft; check attachments by 19 Oct |

Dates are invented project-specific diary entries, not JCT, NEC or FIDIC default periods. Keep the rule, date calculation and service evidence together.

## Understanding your results

Dates are invented project-specific diary entries, not JCT, NEC or FIDIC default periods. Keep the rule, date calculation and service evidence together.

## How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the [related guidance](<https://www.quantsurv.com/contract-review/tips/diarise-notices-and-time-bars>) for the context and checks behind this template.

If you need help preparing or reviewing the project records, our [quantity surveying services](<https://www.quantsurv.com/quantity-surveying>) explain the tasks available under a separate appointment. Agree the deliverable, responsibilities and required specialist input before work starts.

[Browse the Library](<https://www.quantsurv.com/library>)