# Measured mile comparison

Compare labour productivity in comparable unaffected and affected work, with the selection and adjustment basis visible.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>) · About 2 min readShare

## How to use it

Choose genuinely comparable work and record differences in scope, team, location and conditions. Validate the comparison before attributing any difference to an event.

### Measured mile comparison

Choose genuinely comparable work and record differences in scope, team, location and conditions. Validate the comparison before attributing any difference to an event.

[Download blank Excel workbook](<https://www.quantsurv.com/downloads/library/measured-mile-comparison.xlsx>)

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

#### Measured mile comparison

Scroll across if needed to read the whole record. A dash means no value has been entered.

Measured mile comparison: completed fictional example
| Work sample | Output (m²) | Actual hours | Hours per m² | Baseline hours per m² | Expected hours | Excess hours | Evidence / comparability |
| --- | --- | --- | --- | --- | --- | --- | --- |
| Unaffected Level 1 | 200 | 100 | 0.5 | 0.5 | 100 | 0 | Same partition type and team; D-01 to D-05 |
| Affected Level 2 | 160 | 120 | 0.75 | 0.5 | 80 | 40 | Same specification; access interruptions D-10 to D-14 |

The example shows 40 excess hours against the selected baseline. It does not prove that all 40 hours were caused by a compensable event. Explain adjustments and other causes.

## Understanding your results

The example shows 40 excess hours against the selected baseline. It does not prove that all 40 hours were caused by a compensable event. Explain adjustments and other causes.

## How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the [related guidance](<https://www.quantsurv.com/delay-and-disruption/faq/what-is-measured-mile-analysis>) for the context and checks behind this template.