# Late payment interest calculator

Estimate statutory interest and fixed compensation on an eligible late payment. Check the applicable interest terms before relying on the result.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>) · About 3 min readShare

## How to use it

Enter one late payment to see the statutory interest at 8% above base rate and the fixed compensation, with the working.

Sum owed (£)

The unpaid amount, including VAT if it was invoiced with VAT.

Date it was due

For a payment under a construction contract, this is the final date for payment.

Date paid

Leave this blank if it is still unpaid, and we count to today.

Bank of England base rate (%)

Enter the base rate in force on the 30 June or 31 December before interest started. Look it up in the [Bank of England’s Bank Rate history](<https://www.bankofengland.co.uk/boeapps/database/Bank-Rate.asp>).

### The working

Enter the sum, the date it was due and the base rate. The working appears here.

The rate is the base rate on that date plus 8%, and it stays the same for as long as the debt is unpaid. It is simple interest, worked out day by day.

The fixed sum is £40, £70 or £100, by the size of the debt. You can also claim reasonable costs of recovering the debt, where the fixed sum does not cover them.

If your contract sets its own remedy for late payment, and that remedy is substantial, it applies instead of statutory interest.

This is for guidance only. It follows the Late Payment of Commercial Debts (Interest) Act 1998, but it is not legal advice. Check the dates and the rate against your own contract before you claim.

## Understanding your results

The total separates interest from fixed compensation. Check the principal, rate and late-payment period against your records before using it. A calculated figure does not establish that statutory interest applies or that the underlying debt is owed. Keep the working with the relevant invoice and payment record.

## How it works

Enter the sum outstanding, the date it was due and the date it was paid, if it ever was. For a payment under a construction contract, the date it was due is the final date for payment. It is the last day the other party can pay without being late.

The calculator counts the days late. It then applies the Bank of England base rate you enter, plus the 8% that [article 4 of the Late Payment of Commercial Debts (Rate of Interest) (No. 3) Order 2002](<https://www.legislation.gov.uk/uksi/2002/1675/article/4>) adds on top.

[Section 5A of the Late Payment of Commercial Debts (Interest) Act 1998](<https://www.legislation.gov.uk/ukpga/1998/20/section/5A>) adds fixed compensation for each debt on top of the interest. Where the payment is still unpaid, the working also shows what each extra day adds. The result is an estimate, not a decision that the debt or interest is legally due.

Check whether statutory interest applies to the debt, including any contractual interest remedy. Preserve your invoice, payment terms and payment record with the calculation.

For an unpaid balance, [Overdue payment recovery](<https://www.quantsurv.com/claims?service=%2Fnot-paid%2Fservices%2Flate-payment-recovery#client-types>) considers those records alongside the debt itself. Interest is one part of the account, not a substitute for establishing what is owed.

## Sources

1.  [Late Payment of Commercial Debts (Rate of Interest) (No. 3) Order 2002, SI 2002/1675, art 4 (Rate of statutory interest)](<https://www.legislation.gov.uk/uksi/2002/1675/article/4>). legislation.gov.uk.
2.  [Late Payment of Commercial Debts (Interest) Act 1998, s 5A (Compensation arising out of late payment)](<https://www.legislation.gov.uk/ukpga/1998/20/section/5A>). legislation.gov.uk.

[Browse the Library](<https://www.quantsurv.com/library>)