# Final account covering letter

Submit a reconciled final account while identifying amounts that remain disputed or reserved.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>) · About 2 min readShare

## How to use it

Attach the actual account and evidence index. Match any reservation to the intended scope and obtain review before accepting final settlement wording.

### Final account covering letter

Attach the actual account and evidence index. Match any reservation to the intended scope and obtain review before accepting final settlement wording.

[Download blank Word template](<https://www.quantsurv.com/downloads/library/final-account-covering-letter.docx>)

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

#### Document details

Project

Westhaven refurbishment

From

Westhaven Interiors Ltd, commercial team

To

Alder Mere Projects Ltd, project commercial lead

Date

14 October 2026

Reference

WH-54-01

#### Subject: proposed final account FA-01

We submit final account FA-01 for order WH-042. The proposed gross value is £221,000 excluding VAT: £200,000 original sum, £18,000 agreed changes and £3,000 unresolved additional work.

Payments received total £190,000 and retention held is £10,900. The proposed balance excluding retention is £20,100. These figures are reconciled in the attached account and payment register.

The £3,000 item CH-12 remains disputed. Please provide your itemised response and supporting records. This submission is a proposal for assessment; it does not record acceptance of a general release or settlement of unspecified claims.

The completed example uses fictional people, events and records. Replace it with your own verified information and preserve supporting evidence.

## Understanding your results

The completed example uses fictional people, events and records. Replace it with your own verified information and preserve supporting evidence.

## How it works

The Word file provides an unpopulated working structure to complete for your project. The completed fictional example stays on this page.

Read the [related guidance](<https://www.quantsurv.com/final-accounts/faq/subcontractor-final-account-dispute-letter>) for the context and checks behind this template.

If you need help preparing or reviewing the project records, our [quantity surveying services](<https://www.quantsurv.com/quantity-surveying>) explain the tasks available under a separate appointment. Agree the deliverable, responsibilities and required specialist input before work starts.

[Browse the Library](<https://www.quantsurv.com/library>)