# Estimate review checklist

Review scope, quantities, rates, allowances and exclusions before relying on an estimate.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>) · About 2 min readShare

## How to use it

Use an independent check where possible. Record the source, issue and action for each review point instead of marking a box without evidence.

### Estimate review checklist

Use an independent check where possible. Record the source, issue and action for each review point instead of marking a box without evidence.

[Download blank Excel workbook](<https://www.quantsurv.com/downloads/library/estimate-review-checklist.xlsx>)

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

#### Estimate review checklist

Scroll across if needed to read the whole record. A dash means no value has been entered.

Estimate review checklist: completed fictional example
| Review area | Check performed | Finding | Action / owner | Status |
| --- | --- | --- | --- | --- |
| Scope | Compare estimate with drawing register C | Services shown but no priced item | Estimator to add services allowance | Open |
| Quantities | Check partition take-off M-01/M-02 | 80 m² reconciles to measured sheets | Retain checked take-off | Complete |
| Rates | Review supplier quotation dates | Board quote expires 30 Oct | Reconfirm before order | Open |
| Risk and tax | Review risk register and tax basis | Ground risk separate; VAT excluded | Confirm funding budget includes applicable VAT | Open |

The completed example uses fictional people, events and records. Replace it with your own verified information and preserve supporting evidence.

## Understanding your results

The completed example uses fictional people, events and records. Replace it with your own verified information and preserve supporting evidence.

## How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the [related guidance](<https://www.quantsurv.com/library/construction-estimating-mistakes>) for the context and checks behind this template.

If you need help preparing or reviewing the project records, our [quantity surveying services](<https://www.quantsurv.com/quantity-surveying>) explain the tasks available under a separate appointment. Agree the deliverable, responsibilities and required specialist input before work starts.

[Browse the Library](<https://www.quantsurv.com/library>)