# Construction cash-flow forecasting

Forecast the cash balance from dated receipts and payments, then test what happens when a receipt is delayed.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>) · About 2 min readShare

## How to use it

Use bank cash and expected payment dates, not earned value. Carry each closing balance into the next opening balance and show any funding gap.

### Construction cash-flow forecasting

Use bank cash and expected payment dates, not earned value. Carry each closing balance into the next opening balance and show any funding gap.

[Download blank Excel workbook](<https://www.quantsurv.com/downloads/library/construction-cash-flow-forecast.xlsx>)

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

#### Construction cash-flow forecasting

Scroll across if needed to read the whole record. A dash means no value has been entered.

Construction cash-flow forecasting: completed fictional example
| Period / scenario | Opening cash (£) | Receipts (£) | Payments (£) | Closing cash (£) | Timing / action |
| --- | --- | --- | --- | --- | --- |
| October baseline | £20,000.00 | £60,000.00 | £70,000.00 | £10,000.00 | Includes £25,000 client receipt expected 16 Oct |
| October delayed receipt | £20,000.00 | £35,000.00 | £70,000.00 | \-£15,000.00 | £25,000 moves to November; arrange £15,000 funding or reschedule outflows |
| November after delay | \-£15,000.00 | £75,000.00 | £50,000.00 | £10,000.00 | Includes delayed £25,000; opening equals October delayed close |

The first two rows are alternative scenarios, not consecutive periods. The November row follows the delayed scenario. Include VAT in cash flows where actually payable or recoverable.

## Understanding your results

The first two rows are alternative scenarios, not consecutive periods. The November row follows the delayed scenario. Include VAT in cash flows where actually payable or recoverable.

## How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the [related guidance](<https://www.quantsurv.com/library/construction-cash-flow-forecast>) for the context and checks behind this template.