# Builder stage payment schedule

Connect each proposed stage payment to a measurable milestone, evidence, assessment and actual receipt.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>) · About 2 min readShare

## How to use it

Agree objective completion evidence and payment terms before work starts. Record whether a stage is complete rather than paying solely because its forecast date has arrived.

### Builder stage payment schedule

Agree objective completion evidence and payment terms before work starts. Record whether a stage is complete rather than paying solely because its forecast date has arrived.

[Download blank Excel workbook](<https://www.quantsurv.com/downloads/library/builder-stage-payment-schedule.xlsx>)

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

#### Builder stage payment schedule

Scroll across if needed to read the whole record. A dash means no value has been entered.

Builder stage payment schedule: completed fictional example
| Stage / trigger | Stage amount (£) | Assessed (£) | Paid (£) | Assessed balance (£) | Evidence / date | Status |
| --- | --- | --- | --- | --- | --- | --- |
| Foundations complete | £15,000.00 | £15,000.00 | £15,000.00 | £0.00 | Inspection record F-01; 30 Sep | Complete and paid |
| Structure watertight | £25,000.00 | £20,000.00 | £10,000.00 | £10,000.00 | Inspection S-01; roof detail outstanding | Part assessed; clarify remaining scope |
| Practical completion | £10,000.00 | – | £0.00 | – | Completion evidence not yet available | Not yet assessed |

Example amounts exclude VAT. A stage amount is not automatically payable in full where the agreed trigger has not occurred. Apply the actual contract payment process.

## Understanding your results

Example amounts exclude VAT. A stage amount is not automatically payable in full where the agreed trigger has not occurred. Apply the actual contract payment process.

## How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the [related guidance](<https://www.quantsurv.com/library/payment-and-notices>) for the context and checks behind this template.