# Area handover record

Record the condition of a completed area, outstanding items and responsibility for protection at handover.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>) · About 2 min readShare

## How to use it

Inspect jointly where possible. Describe the scope of acknowledgement and preserve dated photographs rather than implying that every obligation is discharged.

### Area handover record

Inspect jointly where possible. Describe the scope of acknowledgement and preserve dated photographs rather than implying that every obligation is discharged.

[Download blank Word template](<https://www.quantsurv.com/downloads/library/area-handover-record.docx>)

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

#### Area handover record

Scroll across if needed to read the whole record. A dash means no value has been entered.

Area handover record: completed fictional example
| Field | Completed fictional record |
| --- | --- |
| Area / date | Level 1 east corridor; 12 October 2026, 14:00 |
| Work inspected | Partition installation to P-104 D; painted finish excluded |
| Condition | No visible damage at inspection; access panels operational |
| Outstanding items | Two label plates to fit by 16 October; snag S-04 |
| Evidence | Photos P-1201 to P-1206; joint inspection HR-01 |
| Protection | Contractor site lead takes control of area protection from 14:00 |
| Acknowledgement | A. Reed and C. Morgan acknowledge recorded condition only; payment and contractual completion assessed separately |

The completed example uses fictional people, events and records. Replace it with your own verified information and preserve supporting evidence.

## Understanding your results

The completed example uses fictional people, events and records. Replace it with your own verified information and preserve supporting evidence.

## How it works

The Word file provides an unpopulated working structure to complete for your project. The completed fictional example stays on this page.

Read the [related guidance](<https://www.quantsurv.com/contra-charges/tips/sign-off-finished-areas>) for the context and checks behind this template.

If you need help preparing or reviewing the project records, our [quantity surveying services](<https://www.quantsurv.com/quantity-surveying>) explain the tasks available under a separate appointment. Agree the deliverable, responsibilities and required specialist input before work starts.

[Browse the Library](<https://www.quantsurv.com/library>)