# Acceleration and mitigation appraisal

Compare the additional cost, time benefit and authority for proposed recovery options before committing resources.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>) · About 2 min readShare

## How to use it

Price each option against the same baseline. Separate forecast savings from assured savings and record who authorises the chosen action.

### Acceleration and mitigation appraisal

Price each option against the same baseline. Separate forecast savings from assured savings and record who authorises the chosen action.

[Download blank Excel workbook](<https://www.quantsurv.com/downloads/library/acceleration-and-mitigation-appraisal.xlsx>)

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

#### Acceleration and mitigation appraisal

Scroll across if needed to read the whole record. A dash means no value has been entered.

Acceleration and mitigation appraisal: completed fictional example
| Option | Extra labour (£) | Extra plant (£) | Other extra cost (£) | Avoided cost (£) | Net extra cost (£) | Forecast time benefit / basis | Decision / authority |
| --- | --- | --- | --- | --- | --- | --- | --- |
| Resequence adjacent area | £500.00 | £0.00 | £0.00 | £300.00 | £200.00 | 1 day; planner review P-03 | Approved operational mitigation 14 Oct |
| Weekend shift | £2,400.00 | £400.00 | £200.00 | £600.00 | £2,400.00 | 2 days; access and supervision required | Proposal only; no instruction |

Costs exclude VAT. Do not assume that a request to recover progress agrees acceleration costs or changes the completion date.

## Understanding your results

Costs exclude VAT. Do not assume that a request to recover progress agrees acceleration costs or changes the completion date.

## How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the [related guidance](<https://www.quantsurv.com/delay-and-disruption/faq/acceleration-costs>) for the context and checks behind this template.