# When a contract ends or a contractor becomes insolvent

A stopped project, an ended contract and an insolvent contractor raise different questions. Establish which one you face before deciding what to do.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>) · About 4 min readShare

## The answer

Termination ends performance under an applicable contractual or legal right. Suspension pauses some or all performance under its own rules. Insolvency concerns the financial position or a formal procedure affecting the business. These events can overlap, but an unpaid bill or a rumour that a contractor has failed does not establish which has happened. Payment, possession of materials and the remaining work need to be assessed under the actual agreement and procedure.

## Identify what has happened

Save the notice or announcement and record who issued it. Distinguish a suspension instruction, default notice, termination notice and formal insolvency appointment.

[Companies House guidance](<https://www.gov.uk/government/publications/liquidation-and-insolvency/liquidation-and-insolvency>) explains different company procedures. Confirm the entity and process rather than relying on a trading name.

An unpaid invoice and formal insolvency are not the same thing. Your response depends on the process, contract and governing law.

If your builder has gone bust, confirm the business identity and the actual insolvency event. A rumour or unanswered telephone is not confirmation.

Distinguish a company from an individual trading under a business name. Obtain advice about the proper office-holder, creditor process and any live deadlines.

## Check before stopping or terminating

Identify the alleged breach, required notice, remedy period and service method. Treat a contested notice as urgent without accepting its allegations automatically.

Where applicable, [section 112 of the Housing Grants, Construction and Regeneration Act 1996](<https://www.legislation.gov.uk/ukpga/1996/53/section/112>) concerns suspension for non-payment. Suspension and termination are different rights.

Insolvency can affect enforcement and contractual termination rights. Obtain legal advice before relying on an insolvency clause or taking possession of goods.

## Preserve the commercial record

Record work completed, outstanding work, materials, plant, site condition and access arrangements. Keep photographs, delivery records and ownership documents.

Separate unpaid applications, retention, disputed changes and alleged deductions. Record payments received after the event against the correct items.

Check instructions from the authorised person before returning, removing equipment or incurring more cost. Deal with immediate safety duties appropriately.

For a home project, photograph the current work and list unfinished or defective items. Keep the contract, deposit receipts, payment history, materials records and correspondence.

Check warranty and insurance notification requirements promptly. Have ownership and access rights checked before removing disputed materials or paying someone else to use them.

Obtain a defined cost-to-finish scope, separating unpaid original work from remobilisation and rectification. A replacement quotation is not automatically recoverable in full.

Keep the commercial records and valuation separate from the legal decision to terminate. Insolvency and termination decisions require specialist advice.

These records support the valuation work involved in [Termination account preparation and assessment](<https://www.quantsurv.com/claims?service=%2Ftermination%2Fservices%2Ftermination-recovery#client-types>). Insolvency procedures and decisions about terminating still need appropriate specialist advice.

## Understand the creditor process

Identify the appointed office-holder and their instructions for submitting a claim. Keep copies of the evidence and correspondence supplied.

The [Insolvency Service creditor guidance](<https://www.gov.uk/guidance/technical-guidance-for-official-receivers/43-creditors-and-liabilities>) explains provable liabilities. Admission of a debt does not guarantee payment in full.

Different procedures and jurisdictions have different restrictions and priorities. Scotland and Northern Ireland require their applicable rules to be checked.

## Example

### The facts

A roofing subcontractor hears that their main contractor has entered administration while £18,000 remains disputed or unpaid.

### What happens

1.  They verify the company and appointment, then save the administrator contact details.
    
2.  They record installed work and separate their own hired equipment from materials whose ownership needs checking.
    
3.  They prepare their account evidence and seek advice on the subcontract before stopping, terminating or removing goods.
    

### What this shows

The subcontractor has a documented position and identified decision points. The example predicts no distribution or recovery.

## Sources