# Notice of adjudication

The notice identifying the dispute to be adjudicated and the remedy sought, starting the applicable procedural timetable.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>) · About 3 min readShare

## Further detail

Read this alongside [paragraph 1 of Part I of the Scheme for Construction Contracts (England and Wales) Regulations 1998](<https://www.legislation.gov.uk/uksi/1998/649/schedule/part/I/paragraph/1>) and [paragraph 7 of Part I of the Scheme for Construction Contracts (England and Wales) Regulations 1998](<https://www.legislation.gov.uk/uksi/1998/649/schedule/part/I/paragraph/7>).

The notice identifies the dispute being referred and the remedy sought. Under the England-and-Wales Scheme, the referral must follow within seven days of the notice. Appointment and service need careful coordination; a poorly defined notice can create jurisdictional or procedural disputes.

Check the applicable rules before starting the clock. A [Claim viability review](<https://www.quantsurv.com/express-services/claim-viability-review>) can organise the underlying claim, while formal procedure may require specialist advice.

## Sources

1.  [Scheme for Construction Contracts (England and Wales) Regulations 1998, SI 1998/649, Schedule, Part I, para 1 (Notice of intention to seek adjudication)](<https://www.legislation.gov.uk/uksi/1998/649/schedule/part/I/paragraph/1>). legislation.gov.uk.
2.  [Scheme for Construction Contracts (England and Wales) Regulations 1998, SI 1998/649, Schedule, Part I, para 7 (Referral of the dispute)](<https://www.legislation.gov.uk/uksi/1998/649/schedule/part/I/paragraph/7>). legislation.gov.uk.

### Formal communication preparation pack

Use these original fictional preparation records to organise the evidence and obtain advice on the actual procedure. They are not universal notices to serve.

[Download blank Word template](<https://www.quantsurv.com/downloads/library/formal-communication-preparation-pack.docx>)

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

#### Dispute notice preparation

Scroll across if needed to read the whole record. A dash means no value has been entered.

Dispute notice preparation: completed fictional example
| Field | Completed fictional record |
| --- | --- |
| Parties and contract | Westhaven Interiors and Alder Mere Projects; order WH-042 |
| Dispute | £2,000 September assessment difference, rejected in response C-11 |
| Relief sought | Payment of the substantiated balance; interest basis to be checked |
| Documents | APP-09, PN-09, C-09 and C-11; bank record B-17 |
| Procedure | Identify applicable adjudication terms, nominating route and service requirements before issuing |

#### Suspension review

Scroll across if needed to read the whole record. A dash means no value has been entered.

Suspension review: completed fictional example
| Check | Completed fictional record |
| --- | --- |
| Payment position | £2,000 assessed balance unpaid; application difference tracked separately |
| Prerequisites | Payment obligation, final date and any pay less notice to be reviewed |
| Proposed action | No suspension date authorised; review notice period and service first |
| Operational plan | Record affected work, safe handover and restart implications |

#### Termination review

Scroll across if needed to read the whole record. A dash means no value has been entered.

Termination review: completed fictional example
| Check | Completed fictional record |
| --- | --- |
| Alleged ground | Repeated access obstruction alleged; contract ground not yet established |
| Sequence | Review breach notice, remedy opportunity and termination steps separately |
| Authority | Decision and wording require authorised review before any notice |
| Evidence / account | Preserve correspondence, programme, work/property inventory and payment account |

These preparation examples deliberately stop before a legal act. The applicable contract, governing law and facts determine the required content, procedure and consequences.