# Activity schedule

In an NEC contract under Option A or C, the list of activities, each with a price, that makes up your price.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>) · About 2 min readShare

## Further detail

Read this alongside [the NEC Dictionary of Terms](<https://www.neccontract.com/resources/dictionary>).

An activity schedule connects the price to identifiable parts of the work. It is not the same as the programme, which explains sequencing and timing. NEC Option A and Option C use the schedule differently, so do not assume the same payment assessment applies to both.

Check how activities are described and when they qualify for payment. Our [Subcontract payment assessments](<https://www.quantsurv.com/quantity-surveying?service=%2Fquantity-surveying%2Fpayment-applications-valuations#client-types>) service keeps the activity assessment and other adjustments traceable to the agreed mechanism.

## Sources

1.  [NEC Dictionary of Terms](<https://www.neccontract.com/resources/dictionary>). NEC Contracts.

### Activity schedule and rates examples

Use the pricing document required by your contract. Record completion criteria for activities and measurement rules for rate-based items.

[Download blank Excel workbook](<https://www.quantsurv.com/downloads/library/activity-schedule-and-rates-examples.xlsx>)

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

#### Activity schedule

Scroll across if needed to read the whole record. A dash means no value has been entered.

Activity schedule: completed fictional example
| Activity | Completion criterion | Price (£) | Position at cutoff | Evidence |
| --- | --- | --- | --- | --- |
| A-01 foundations | Foundations complete and inspection accepted | £15,000.00 | Complete | F-01 |
| A-02 envelope | Roof and external walls watertight | £25,000.00 | Incomplete | Roof detail outstanding |

#### Schedule of rates

Scroll across if needed to read the whole record. A dash means no value has been entered.

Schedule of rates: completed fictional example
| Item | Description | Measured quantity | Unit | Rate (£) | Measured value (£) |
| --- | --- | --- | --- | --- | --- |
| R-01 | Partition finish | 80 | m² | £25.00 | £2,000.00 |
| R-02 | Special finish | 20 | m² | £40.00 | £800.00 |

The examples illustrate pricing structures. They do not establish when an incomplete activity is payable or which quantities are contractually remeasurable.