# Liquidated damages (LDs)

An agreed contractual measure of damages for a specified breach, commonly delay, subject to the relevant conditions.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>) · About 1 min readShare

## Further detail

Read this alongside [SCL Delay and Disruption Protocol](<https://www.scl.org.uk/sites/default/files/documents/SCL_Delay_Protocol_2nd_Edition_Final.pdf>).

Liquidated damages set an agreed measure for a defined breach, often delay to completion. The contractual trigger, applicable completion date and notice requirements still need to be satisfied. An agreed rate avoids quantifying actual loss in that way, but does not make every proposed deduction valid.

Check extensions of time and the period claimed before calculating the exposure. [Delay damages review and response](<https://www.quantsurv.com/claims?service=%2Fliquidated-damages%2Fservices%2Fdelay-damages-recovery#client-types>) examines the basis and evidence for a disputed deduction.