# Keep entitlement and quantum separate

Explain why an amount is due, then how you calculated it. Keeping entitlement and value distinct helps both sides identify what they actually disagree about.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## Why

If the other party does not accept that you are owed anything, it will happily spend the meeting on your rates. Every hour spent on the number is an hour in which the principle is never conceded. Write the two arguments together and a weak rate becomes a reason to doubt the event. A doubted event becomes a reason to pay nothing. Keep them apart and the principle can be agreed on its own, under the contract or at law. The talk about money then starts from a conceded principle, and the only question left is how much.

## How do I do it?

1.  Write the case for each head's principle first: the event, the contract basis, the notice given and the record of what caused it.
2.  Write the money side separately: the build-up, the records and the source of every rate.
3.  Ask the other party to agree the principle, head by head, before any meeting on value.
4.  Record the precise scope and any qualification of each agreement before moving to the number.
5.  Answer valuation points on their merits while checking whether new evidence affects an assumption or qualification in the earlier agreement.

Our [Final account dispute assessment and response](<https://www.quantsurv.com/claims#client-types>) tests the contractual basis and valuation as separate questions within the same account.

[Browse completion and contract endings in the Library](<https://www.quantsurv.com/library#topic-completion>)

[Browse the Library](<https://www.quantsurv.com/library>)