# Check the machinery before the merits

Before arguing the numbers, check that your contract still lets you bring each head at all. A missed notice, a condition precedent, a final certificate gone conclusive or a signed settlement can close a claim before anyone looks at the merits.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 9 October 2026 · About 2 min readShare

## Why

Contracts close doors quietly. Some make a notice a condition precedent: a step that must be taken before a claim can succeed at all. A claim not notified in time. A final certificate that became conclusive while nobody was watching. A settlement letter that said everything was resolved. Each can kill a head before anyone reads the merits. A strong case built on a closed head is wasted twice: once in preparation, and again when the other side raises the time bar in its first paragraph. So check the procedure first. Its effect may need legal assessment of the wording, service, exceptions and conduct before you decide how to proceed.

## How do I do it?

1.  List the contract's notice, claim and condition precedent rules for each head, and the dates they fell.
2.  Check the correspondence file for the notice or claim that met each rule, and note its date.
3.  Check whether any certificate has become conclusive, and whether any settlement or waiver wording has been signed.
4.  Refer anything unclear to your solicitor before spending money on the merits.
5.  Drop or reframe any head where the route is closed, and put the effort into the heads that remain open.

Our [Final account dispute assessment and response](<https://www.quantsurv.com/claims#client-types>) checks notices, payment procedures and live deadlines alongside the underlying account merits.

[Browse completion and contract endings in the Library](<https://www.quantsurv.com/library#topic-completion>)

[Browse the Library](<https://www.quantsurv.com/library>)