# What should a final account dispute letter say?

It should set out your account, their assessment, every difference with your reasons and evidence, the sum due and a date to reply.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 12 October 2026 · About 2 min readShare

## The answer

A final account dispute letter should set out your account, their assessment, every difference with your reasons and evidence, the sum due and a date to reply. Think of it as a reconciliation with a request at the end, not an argument.

Open with the two figures: the final account you submitted and its date, and the assessment and its date. Then list every line where they differ, in the order of the account. Against each, give three things. First, the amount of the difference. Second, the basis for your figure: the instruction, the measure, the rate or the clause. Third, the reference to your evidence. Where you accept an item, say so. Conceding the weak lines is what makes the strong ones believable.

Close with the sum you say is due, a clearly labelled requested date for agreement or a reasoned reply, and the next action you are considering. Check any shorter contractual or legal deadline and the requirements for that action.

Keep it flat and factual. An adjudicator or a solicitor will read it before long, and a calm, dated statement will count for more then than a page of grievance. Attach the schedule of differences rather than burying it in the text.

### Attach a line-by-line reconciliation

A covering letter is easier to assess when its figures can be traced. Prepare a final account reconciliation to compare the two valuations using common item references.

Identify agreed sums, disputed valuations and unsupported deductions separately. Reconcile payments and retention before stating the balance sought. Give each requested correction an evidence reference and a clear reason, and check contractual deadlines before deciding when to respond.

[Final account dispute assessment and response](<https://www.quantsurv.com/claims#client-types>) produces that schedule of differences, with the evidence checked, before the letter goes.

[Browse completion and contract endings in the Library](<https://www.quantsurv.com/library#topic-completion>)

[Browse the Library](<https://www.quantsurv.com/library>)