# What can I do if the other party ignores my final account?

Check what your contract required the other party to do and by when, then stop chasing and write once, formally.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 9 October 2026 · About 2 min readShare

## The answer

Start with the contract's final payment terms. Did the other party have to respond within a set period? Does its silence have any stated effect? Which dates and notices apply to the final payment? Some contracts are precise and some say little. If yours says nothing, find out which payment rules apply before you rely on any date.

Then write the formal letter. Set out the account you submitted and its date, and each chaser since. Give the sum you say is due and why, and a date for agreement or a reasoned reply. Attach an itemised evidence schedule so the issues can be assessed, while answering legitimate requests for further detail.

Continue interim applications only where the applicable terms permit them, and pursue sums already due through the relevant payment mechanism. An open final account does not suspend the payment notices under the [Housing Grants, Construction and Regeneration Act 1996](<https://www.legislation.gov.uk/ukpga/1996/53/section/111n1>).

If the silence goes on, you can refer the dispute to adjudication at any time under [section 108](<https://www.legislation.gov.uk/ukpga/1996/53/section/108>), subject to the applicable jurisdiction and dispute requirements. Have the representative check whether to refer the account or a properly defined part of it. Your unanswered letters are part of the record. Silence does not stop the clock on a conclusive evidence clause or on limitation, the legal time limit for bringing a claim, so check both with your solicitor.

Our [Final account dispute assessment and response](<https://www.quantsurv.com/claims#client-types>) rebuilds the account item by item and runs the correspondence on a timetable in your name.

## Sources

1.  [Housing Grants, Construction and Regeneration Act 1996, s 111 (Requirement to pay notified sum)](<https://www.legislation.gov.uk/ukpga/1996/53/section/111n1>). legislation.gov.uk.
2.  [Housing Grants, Construction and Regeneration Act 1996, s 108 (Right to refer disputes to adjudication)](<https://www.legislation.gov.uk/ukpga/1996/53/section/108>). legislation.gov.uk.

[Browse completion and contract endings in the Library](<https://www.quantsurv.com/library#topic-completion>)

[Browse the Library](<https://www.quantsurv.com/library>)